Building Progress

Thursday, December 18, 2014

Main Floor & Roof

The days are short but the weather is great, daytime highs in the range of -2 C  to + 4 C so fairly productive days.  The basement is framed, floor joists and sub-floor are in place, upper walls are framed and working on the roof truss package.  We had the crane on site yesterday for about 3 hours lifting the trusses into place.  The crew will be working on the roof sheathing today, Friday and likely most of Monday.