On Monday morning the crew finished cleaning up the site by 10:00 AM the foundation coating was started. Inspections for damp proofing and back fill were approved Monday afternoon. On Tuesday we brought in a number of loads of sand and gravel for under the basement slab, prepared the slab and installed the steel reinforcing bar over the slab seal, inspections for the slab seal were approved Tuesday afternoon. Due to the 6" of snow on Wednesday morning we rescheduled the basement slab pour until Thursday.
On Thursday everything went very smooth, a great looking slab, at the end of the day the tarps were placed on top of the new basement floor.