Building Progress
Wednesday, November 19, 2014
Forming & Inspections
The installation of the steel reinforcing bars was completed this morning and inspections by both the structural engineer and the District of Lake Country was done shortly after lunch. The crew will finish forming the balance of the non-engineered walls today and Thursday. The pour for the walls is scheduled for Friday, stripping of the forms will be done Saturday and Sunday. The rough-in for the plumbing under the slab will be completed by the end of Friday. Foundation coating is scheduled for Sunday afternoon.