The building permit was issued by the District of Lake Country on November 10th and the excavation started on November 11. Site layout shows an elevation change from the high side of the property to the low side of the property of just over 6 ft. We have set the front left corner of the home 10" above the height of the sidewalk. The elevation will accommodate top soil to finished grade and maintain a minimum of 6" from the finished grade to the bottom of the siding. The grade difference from the front left corner of the home to the front left corner of the garage is nearly 3 ft so we will drop the garage about 2' to maintain a more gentle slope to the driveway.